As I stated in the header, I am beginning the design of the new website layout today. Shocking, I know. In order for this to be a success it has to be unique, and I won’t be totally satisfied unless I code it myself. Just like they taught me in school, every project has to start off in a design phase, so I’ll be drawing rough designs this week of the new layout and I’ll get CreatorGX to look it over, since the site will likely be half his within the next few months (If he decides it so).
Any-damn-way, here is a basic idea of my Estimated Work Timeline (or EWT):
1. Design Draft (8/2/2010 – 8/7/2010)
2. Final Draft Agreed upon (8/14/2010)
=Alpha 1=
3. Start/Finish CSS & HTML Design (8/15/2010 – 9/25/2010)
4. Import SQL from forum successfully (10/1/2010 – 10/10/2010)
=Alpha 2=
5. Start/Finish blog code (10/15/2010 – 11/10/2010)
6. Start/Finish forum code (11/13/2010 – 12/25/2010)
=Beta 1=
7. Forum/Site Integration (12/26/2010 – 1/1/2011)
=Beta 2.0=
8. “Achievement” Coding (1/2/2011 – 2/2/2011*)
=Beta 2.5=
9. Bug workarounds/RSS working/Mobile version/Other (2/5/2011 – 3/25/2011)
=@TI v.6.0=
10. Game 1 (4/1/2011 – ???)
=Site Complete(?)=
We certainly won’t be churning out games like crazy given our lengthy pacing, but we will be working on our (estimated) multiple comics, podcasts, (hopefully) videos, and then some. This is the grand scheme I’ve laid out before you. Tell us what you think of it on the forum! I encourage it! (Also tell your friends about us~)
~Nick Out
*New to me, going to take about a month